Yucca project assailed: NRC board hears Nevada's
challenges
Jan 27 - McClatchy-Tribune Regional News - Keith Rogers Las Vegas
Review-Journal
Nevada's lead attorney took a stab Tuesday at killing the Yucca Mountain
nuclear waste project, arguing before a licensing board that the
Department of Energy neglected to consider the failure or absence of a
key safety feature.
Also, Marty Malsch, a lawyer with a Washington, D.C.-area firm retained
by the state, told nuclear regulators the repository's design should be
rejected because it is only 70 percent complete.
Those were two of 11 legal challenges the Nuclear Regulatory
Commission's Construction Authorization Board heard in the first day of
oral arguments. The hearing comes two years after the DOE submitted its
license application for building a repository for the nation's highly
radioactive waste and used reactor fuel at a disposal site inside a
volcanic-rock ridge 100 miles northwest of Las Vegas.
The hearings continue today at the NRC's Las Vegas facility on Pepper
Lane.
Based on questions asked by one of the panel's three judges,
Malsch's most convincing argument dealt with the failure or absence of
11,000 titanium shields that would protect waste containers from
corrosive water, dust and rocks that could fall inside a maze tunnels.
The "drip shields" wouldn't be installed for a century.
Malsch said the repository's design relies heavily on the drip shields,
which are a part of the system of engineered barriers to prevent deadly
radioactive materials from escaping into the environment.
"We're talking a million years, and uncertainties are rampant," Malsch
told the panel, describing how a "defense-in-depth" system must stay
intact long after the initial 10,000-year requirement for containing the
waste.
"Defense in depth is the elephant in the room, and the message from DOE
and (NRC) staff is to ignore that elephant, but you can't," Malsch said.
Without the drip shields, he said, the repository fails to meet the
radiation safety standard.
Administrative Judge Richard Wardwell repeatedly asked DOE and NRC
lawyers how dependent the repository's design is on the drip shields to
ensure it is safe and functions as planned.
"Wouldn't you, as DOE, want to know if the drip shields are providing 99
percent of the protection?" Wardwell asked Donald Silverman, one of two
attorneys representing the Energy Department at Tuesday's hearing.
Silverman answered: "My understanding is that is not what the commission
wanted."
Again Wardwell asked, "If drip shields provide 99 percent of the
protection, wouldn't you want to know that?
Silverman responded: "I imagine we would."
While DOE attempted to consider the probability of the drip shields
failing from corrosion or rock falls after many thousands of years,
Malsch said during his final statement, "they did not evaluate the
absence of the drip shields at the very beginning."
DOE does not plan to install the drip shields for about 100 years after
77,000 tons of used reactor fuel and highly radioactive defense waste
are loaded into the repository.
Malsch and Nevada officials have described the plan as "science
fiction," because the robotic system needed to install the shields in
such a hot, radioactive environment doesn't exist. And they have
questioned the availability of enough titanium to complete the shields.
Perhaps more importantly, Malsch said, no guarantee exists that Congress
would have an appetite or the means to fund construction of the drip
shields.
The licensing panel will have to decide if there is reasonable assurance
that DOE will be able to follow through with its plan and that it will
work as designed.
Decisions on the 11 legal challenges discussed Tuesday aren't expected
for weeks.
Meanwhile, the Obama administration and Energy Secretary Steven Chu
maintain that Yucca Mountain is no longer an option for disposing the
nation's high-level nuclear waste and that a yet-to-be-announced
commission will chart a new strategy for the future.
Bruce Breslow, executive director of the Nevada Agency for Nuclear
Projects and a Yucca Mountain opponent is not so convinced that will
happen.
"Their word is 'off the table,'" he said during a break in the hearing.
"You can always put it back on the table. They haven't said it's dead.
They haven't withdrawn the license (application) and declared the site
unsuitable. That's something the energy secretary could do and that's
something we're urging."
Contact reporter Keith Rogers at krogers@reviewjournal.com or
702-383-0308.
(c) 2009,
McClatchy-Tribune Information Services
|