Sea state may affect 3rd containment option
installation
By Gary Taylor in Houston
July 6 - National Incident Commander Thad Allen said on July 7 that BP
has begun the process of hooking up the Helix producing unit to the
"kill line" of the runaway Macondo well in the Gulf of Mexico.
"There is a partial hookup right now and they can sustain that," Allen
said at a press briefing. "They (BP) will hold on to what they have got.
They are working as hard as possible to complete that connection. We
won't know for several more hours" if the unit can be successfully and
completely connected, he added, noting that completion of the task is,
"weather dependent."
Allen, who was in Houston to meet with BP officials, noted that the
Helix Producer system is designed to increase containment to 53,000 b/d.
It had initially been scheduled to be installed on June 30, but that was
delayed to July 7 because of Hurricane Alex.
The connection would join the Helix Producer on the surface with the
kill line of the Macondo blowout preventer, providing a third method for
containing part of the 35,000-60,000 b/d estimated to be leaking from
the well since the April 20 blowout that destroyed Transocean's
Deepwater Horizon drilling rig.
Two other containment devices have been diverting oil at a measurable
rate of about 25,000 b/d, taking those volumes to two other vessels on
the surface for collection or flaring.
In addition, BP also is working to attempt installation of what would be
a fourth device designed to increase containment to a potential 80,000
b/d by the middle of July if the Coast Guard approves the plan.
Ultimately, however, BP and the Coast Guard have said the only
permanent solution lies with completion of one of two relief wells
drilling to intercept Macondo on the sea floor 4,993 feet below the
surface.
Although the first of the two relief wells is about a week ahead of
schedule, Allen said again on Tuesday that he will not adjust the target
date from the middle of August because the rest of the drilling requires
meeting the most difficult challenge of actually intercepting the
original Macondo wellbore.
In his meetings with BP in Houston this week, Allen will discuss the
risks and rewards of proceeding with the fourth device, which would
involve removal of a current cap and replacement with a tighter sealing
model.
"The question is: 'Do we want to wait and look at capabilities of the
Helix Producer?' Those are the issues I am here to discuss," Allen said.
If they successfully connect the Helix Producer and increase containment
to the 53,000 b/d level, Allen said it might not be worth the risk of
removing a cap that is working in a bid for a tighter fit from a new
one.
But they won't know the results from the Helix Producer-connection
effort for several hours.
"Two connections are required," he said, explaining that BP has already
made a connection with the buoying system and needs only to hook with a
flexible line.
He said: "They are in the process of doing that right now." But added
the sea state is "right on the margin" of five feet, so the outcome
remained uncertain headed into the evening.
|