Apache invokes force majeure on Rowan rig
By Starr Spencer in Houston
June 28 - For the first time since the US government-imposed moratorium
on drilling in the Gulf of Mexico started last month, an E&P company
June 25 invoked force majeure on a shallow-water rig contract.
Meanwhile, oilfield service providers are citing a lack of clarity over
new government regulations.
Contract driller Rowan Companies said in its latest fleet status report
it had received force majeure notice for the Rowan Cecil Provine jackup
rig from big independent Apache Corporation.
Apache, which specializes in exploiting mature properties on the US
Gulf's aging Continental Shelf, had leased the rig for a dayrate in the
low $60,000s until July. It was targeted for use on further development
work at the independent's large Grand Isle block 40 development in 92
feet of water.
As it has during other crises affecting the oil and other energy
markets, such as hurricanes Katrina, Rita and Ike, Platts is producing
this special summary of events surrounding the Deepwater Horizon rig
disaster in the Gulf of Mexico. This special joint edition of Platts
Oilgram News and OPR Extra will be published as frequently as Platts
believes necessary to give its readers a quick summary of developments
surrounding the leak at the wellhead, the growing footprint of the
spill, and the impact these occurrences are having on markets and on US
federal energy policy.
"The rig is under contract at the indicated day rate but is waiting on a
permit," Rowan said in its fleet report.
Rowan added that Apache declared force majeure June 22 and that the
driller is "evaluating its response to this notice."
Drillers have said a three-week moratorium imposed by the US Interior
Department on new permits and wells in the US Gulf in both shallow and
deep waters resulted in a permitting backlog that has persisted even
though the shallow-water part of the moratorium was lifted in late May.
Several force majeure declarations have been made on deepwater rig
contracts, and drillers have said they do not recognize a government
moratorium as a force majeure event.
The deepwater moratorium was extended for six months but US Department
of Interior Secretary Ken Salazar has pledged to revise it (ON 6/24).
But even without a moratorium, permitting for shallow-water wells has
been beset by delays, say industry sources.
Apache, which has leased the Cecil Provine all this year, confirmed it
had declared force majeure, but a spokesman declined further comment.
The Cecil Provine can work in maximum water depths of 300 feet but can
drill to total depths of 30,000 feet.
Rowan said seven of its US Gulf jackup rigs are currently "impacted" by
recent requirements by offshore oversight agency Bureau of Ocean Energy
Management, Regulation and Enforcement (BOEM), formerly known as the US
Minerals Management Service.
Two Rowan rigs are stacked, while two more are contracted but so far do
not have permitted work beyond their current operations, Rowan said in a
June 24 US securities filing. Three more "are under contract but are
waiting on permits," said the driller in its filing.
Grand Isle 40 is a showcase field, one of the larger assets Apache
acquired in its $1.3 billion purchase of Shelf properties from BP in
2006 (ON 4/20/06). The independent plans to drill a development well
there.
While Apache has kept mum on its reasons for invoking force majeure on a
rig whose contract expires shortly, observers believed the company knew
its drilling permit may be further delayed and did not want to continue
paying for a rig it was not using.
"I think Apache's action to declare force majeure is a demonstration of
the growing frustration that operators, as well as drilling contractors,
are feeling at the current state of affairs," Weeden & Company analyist
Geoff Kieburtz said. Kieburtz was referring to new regulations handed
down by the BOEM, including requirements for third-party verification of
blowout preventers on rigs, and other safety regulations. Companies also
have to show proof that well casing designs and cementing procedures are
certified by a professional engineer.
Given these requirements, "my initial impression is (Apache) is trying
to send a message," said Kieburtz. "The confusion and uncertainty that
have been brought about by the changing rules has effectively shut down
operations in the shallow water as the explicit moratorium has shut down
operations in the deepwater."
Randy Stilley, CEO of Seahawk Drilling, said in a telephone interview
June 25 that industry is "gradually working through the confusion" of
new BOEM regulations. He said these regulations were initially issued
"without any clarifications" and left operators and drillers with many
questions on how to implement them.
Stilley said BOEM's requirement that equipment be certified and verified
by third parties "really has slowed things down."
"We've had to get a third-party inspector out on every rig, and also had
to go through and demonstrate our blowout preventers would cut any pipe
we might be using on any well," he said.
"We had to physically demonstrate this while they were on site, for any
anticipated pressure we might have, and (demonstrate the BOP) would hold
to that pressure," he added.
Stilley said he understood these verifications will be required for
every well, but hopes industry will be able to get into a routine that
will speed up the process. The CEO also said he believes the first
shallow-water permit was issued by BOEM on June 25 since the
shallow-water moratorium took effect in early May, and would return one
of his company's idled rigs to work. That permit, to Bandon Oil and Gas,
could not immediately be confirmed by BOEM.
Even so, Stilley said the rig assigned to that well, Seahawk 2004, a
jackup that can work in 200 feet of water, could start work
"immediately," following permit issuance. But the driller would need to
fully crew the rig, which has been partially crewed while awaiting the
permit, he said. The Seahawk 2004 would earn $36,000/d.
The Bandon permit "has been pending for over two months," said Stilley.
"Normally permits take about a week" to issue, once the exploration and
development plan have been approved. He claimed there were over 40
shallow-water permits pending before BOEM since the three-week
moratorium went into effect May 6. BOEM did not immediately respond to
inquiries from Platts on this.
Stilley said Seahawk has three rigs that are currently idle and awaiting
permit issuance. "If we don't get permits issued in the next two to
three weeks, we'll have another two or three rigs go idle," he said.
|