Report: Leaks may affect VY's reliability
May 1 - McClatchy-Tribune Regional News - Bob Audette Brattleboro
Reformer, Vt.
Vermont Yankee personnel responded to a leak of tritiated water in a
timely, appropriate and effective manner, according to Nuclear Safety
Associates in a supplement to the Comprehensive Reliability Assessment
submitted to the state last year.
Nevertheless, it wrote, the plant is potentially susceptible to similar
leaks, which could prove to be a challenge to the plant's continued
reliability.
Nuclear Safety Associates was hired by the state to review Yankee's
reliability, a report that was meant to inform the Legislature, the
Public Service Board and the Department of Public Service in making the
decision whether the nuclear power plant in Vernon should be allowed to
continue to operate past its license expiration date of 2012.
Entergy, which owns and operates the nuclear power plant in Vernon, has
applied to the Nuclear Regulatory Commission to extend the license to
2032, but also needs approval from the state.
Recently, the state Senate voted 26 to 4 against continued
operation. The Public Service Board is in the process of determining
whether the plant should receive a certificate of public good, which
every public utility in the state must have to operate.
"While the occurrence of the leaks is not in and of itself indicative of
a lack of management oversight, more management attention needs to be
applied to detect future leaks at an early stage," wrote NSA. Until
interim and long-term corrective actions
are implemented, stated NSA, reliability of the plant could be affected.
"Although the (advanced off gas) leak investigation and repair was a
significant event, it did not affect the overall reliability of the
plant," it wrote. "To ensure that long-term reliability is not impacted
(Yankee) should increase its focus and improve its methods and practices
for identifying plant leaks at an early stage through more effective
monitoring. Specifically this is associated with all underground piping
(including buried piping) and piping that is not readily accessible for
inspection."
Currently, Entergy is conducting a root cause analysis to identify the
conditions that precipitated the leak.
By the end of June, Entergy is also expected to submit an extent of
condition report "to determine the vulnerability of the plant to similar
leaks " noted NSA.
It will also identify actions necessary to detect and prevent similar
leaks in the future, it stated in the supplementary report.
The supplementary report followed the revelation that there is
underground piping systems at the Yankee plant that carry radionuclides,
contrary to testimony given by Yankee representatives during hearings
before the state last year.
To fulfill the requirements set forth under Act 189, which mandated the
reliability assessment, DPS asked NSA to conduct a review of the plant's
off gas system.
In consultation with the Public Oversight Panel, which was tasked by the
Legislature to review NSA's reliability assessment, DPS also asked for
an evaluation of Yankee's buried piping and tanks inspection program.
NSA concluded that Yankee practices "meet industry standards and in some
cases exceed industry standards."
Even though the areas identified need to be addressed to ensure the
plant will run reliably for another 20 years, "these specific areas will
not prevent (Yankee) from operating reliably over an extended operating
period," wrote NSA.
In the original reliability assessment, NSA concluded that Yankee can be
a reliable station beyond its current operating license providing
Entergy address five areas of concern -- an upgrade of its procedures,
human performance, focused maintenance to the plant's condenser, cooling
towers and its spare main transformer, delays in implementing industry
recognized performance metrics and an ineffective use of change
management.
In the supplementary report, NSA found that "low level repetitive
equipment issues on non-safety related systems are not resolved in a
timely manner and could challenge future plant reliability," which was
identified in the original CRA regarding the cooling towers.
During the supplementary review, NSA determined that components in the
off gas system have also been affected by "long-standing repetitive
issues (which) challenged operations and could have impacted station
reliability."
NSA recommended that Yankee be proactive in monitoring, detecting and
managing leaks in non-readily accessible piping.
NSA concluded that Yankee does not have an effective program or
practices in place for early leak detection and monitoring of
underground and non-readily accessible piping."
None of the three pipe leaks in steam trap drain lines that were
discovered between 2004 and 2006 were discovered by routine inspections
"primarily due to the fact that they were in areas that are not easily
accessible."
"The fact that inspections could not detect the degradation in the pipes
and could not predict or prevent the leaks points to a weakness in
piping inspections and leakage monitoring."
NSA found that despite the leak discovered in the off gas system's steam
trap lines this year, the off gas system is reliable.
Bob Audette can be reached at raudette@reformer.com, or at 802-254-2311,
ext. 273.
(c) 2010,
McClatchy-Tribune Information Services To subscribe or visit go to:
www.mcclatchy.com/
|