Will giant mixers keep nuclear waste stable?

Jan 23 - McClatchy-Tribune Regional News - Craig Welch The Seattle Times

 

It sounds like a sci-fi thriller: Dangerous gases build up in a giant drum of nuclear waste. It explodes and spews contamination, threatening workers or the public. Or it cripples a facility that cost taxpayers $12.2 billion.

It could happen at Hanford's nuclear-waste-disposal plant -- if radioactive material isn't kept stirred.

So engineers years ago proposed a solution. Inside the plant's giant drums they would put pumps that work like giant turkey basters. Using air and suction, they would slurp up and spit out radioactive sludge to keep it constantly churned.

But despite hundreds of millions of tax dollars and nearly a decade of effort, builders haven't proved these "pulse-jet mixers" will work -- and work safely, according to interviews, audits, internal and external project documents and e-mails.

The effort to perfect this mixing system is a case study of Hanford's engineering challenges and helps explain why the site's waste-to-glass project often seems to be in crisis. Tracing this one technical problem reveals how cutting-edge technology and management missteps have led to setbacks, delays, cost-overruns, investigations and accusations of malfeasance.

Walt Tamosaitis, an engineer and high-level manager with one of Hanford's contractors, charges that speaking out about it cost him his career. He since has filed a whistle-blower complaint. An investigation is under way.

Neither the federal Department of Energy (DOE) nor its contractors will comment on his accusation. They maintain they've solved this mixing problem.

But university scientists and experts with several federal offices aren't convinced.

Untested technology

Hanford's treatment plant is supposed to run waste from leaky underground tanks into large drums in a shopping-mall-sized building. There, radioactive elements will be separated and turned into glass.

Along the way, when waste sits in the plant's dozens of holding vessels, pulse-jet mixers will stir them.

Here's why: Hanford's waste holds up to 1,700 pounds of plutonium-239, scattered among 53 million gallons of other poisons. It is a heavy element and will want to settle at the bottom of these drums. Over time, too many particles could gather and trigger a chain reaction.

It happened in Japan in 1999: Reprocessing-plant workers combined too much uranium. Suddenly, there was a flash of blue light and an intense surge of radiation. Two workers were vomiting within the hour. One died in 12 weeks, another in seven months.

That's just one possibility. Particles of plutonium -- or, for that matter, any other heavy element -- also could build up and trap and release hydrogen that could then explode.

Stirring ensures none of these particles accumulate.

But jet mixers have never been used on this scale -- or with such a mix of chemicals and radioactive isotopes.

And some of Hanford's holding vessels are installed in "black cells," areas already expected to be so hot with radioactivity that no human or equipment can get in to fix them. That means nothing must break down during decades of operation.

Plus, these mixers have competing jobs. They must be strong enough to keep waste from clumping -- and delicate enough to not spit out air or particles with too much force. That could ruin the pumps or damage the holding drums, potentially disabling the entire $12.2 billion plant.

Jet mixers were tested back in 2000, but questions emerged. Plant design and construction continued while engineers tried to answer them.

In the mid-2000s, mixers still had problems. Bechtel National, the lead contractor, set about redesigning them. But because construction had continued, the Government Accountability Office, the investigative arm of Congress, said the redesign and delay drove costs up by $300 million.

Bechtel led parts of a tour of the treatment plant, but declined to answer follow-up questions for this story.

In 2005, the DOE assembled experts to identify major issues facing the plant. Engineer Walt Tamosaitis, who worked for a Bechtel subcontractor, led the group. It came up with 28, including the pulse-jet mixers. The DOE set a deadline to find solutions. It came and went. In 2009 DOE's research arm, the Pacific Northwest National Laboratory (PNNL), showed jet mixers still failed tests.

That's when Tamosaitis, at the request of DOE, stepped back in. He would later accuse the DOE, Bechtel and subcontractor URS of harassing him for raising safety issues.

Computer vs. lab tests

He recounts what happened like this: Bechtel managers wanted to perform tests based on computer models. Tamosaitis insisted on large-scale lab tests. The man overseeing the project for Bechtel said he'd use influence with a DOE official to make sure any fix the company proposed was approved. Otherwise, DOE might withhold some portion of a $6.3 million payment. Another manager said resolving the mixing problem was so tied to compensation and career advancement that if the issue "doesn't close, I'll be selling Amway in Tijuana," according to Tamosaitis' complaint.

Last February, Tamosaitis complained proposed tests remained inadequate. In a June critique, a PNNL researcher said Bechtel took a "razor's edge" approach to safety and left not a whisker of room for error.

Still, on June 30, the new deadline, Bechtel offered its new plans. Bechtel hadn't solved every problem, but the company said it had a path forward, and that's all DOE required.

The next day, Tamosaitis pointed out important issues remained. One day later, Tamosaitis said, he was told to return his badge and phone and was escorted off site and told to report for work in the basement of another building. He said it is a "do-nothing" job.

Weeks later a review by university scientists said Bechtel's lack of massive full-scale tests was risky. The Defense Nuclear Facilities Safety Board, a federal panel appointed by the White House, agreed. In October, a scientist representing the board said Bechtel was "moving construction forward with significant technological risk and uncertainty."

Energy Department officials, another team of scientists and plant contractors disagreed. But "we recognize there is room for questions," said Delmar Noyes, DOE's deputy plant manager, in an interview. The DOE and Bechtel have agreed to conduct new tests.

Just before Christmas, the safety board outlined precisely how it hopes those tests will go because others "have been insufficient." The board reiterated its fear of explosions and chain reactions.

Those large-scale tests may take two years.

Meanwhile, plant construction will continue.

(c) 2010, McClatchy-Tribune Information Services  To subscribe or visit go to:  www.mcclatchy.com/