I'm awarding two black eyes-one for Xcel Energy
and one for the Colorado Public Utilities Commission
(CPUC)-for failure to manage a smart grid pilot.
That's my conclusion from reading the
CPUC's "Order on Exceptions," which is the
written decision and rationale for the CPUC's verbal
decision (announced last month) to cap cost recovery
for Xcel's SmartGridCity project.
By now readers are familiar with the
SmartGridCity project in Boulder, Colo., which
was to be a relatively large-scale pilot to
demonstrate distribution system advancements and
efficiencies, including homeowner energy management.
The project initially was estimated to cost about
$100 million, with only $15 million on Xcel's tab.
Long story short, over time that $15 million tab
mushroomed to more than $45 million and Xcel
retroactively filed for a certificate of public
convenience and necessity (CPCN) to recover $44.5
million. Last fall, Xcel, the CPUC staff and the
Governor's Energy Office proposed a settlement
awarding Xcel that $44.5 million. A CPUC
administrative law judge recommended that the
settlement be granted.
Several groups objected, including the Colorado
Office of Consumer Counsel, the Climax Molybdenum
Company and CF&I Steel (two of Colorado's largest
electricity users) and Leslie Glustrom, a tenacious
citizen. Each filed objections to the recommended
settlement, with various suggestions for appropriate
cost recovery.
As noted, the CPUC overruled its ALJ in early
January and granted Xcel cost recovery of $27.9
million, with the chance to recover another $16.6
million if Xcel could establish ratepayer benefits
from SmartGridCity. (Xcel's Colorado ratepayer base
is 1.4 million electricity accounts.) The $27.9
million cost recovery is the exact amount proposed
by the Colorado Office of Consumer Counsel.
The Demands
As we'll see, the CPUC now has made some demands on
Xcel to engage stakeholders and report on its
SmartGridCity findings, which in my view should have
been instituted at the very beginning of the entire
process.
In the CPUC's written decision, filed last week, the
commission rejected all the "exceptions"-i.e., legal
objections-filed by the various parties to this
case. Yet it imposed the $27.9 million cost recovery
cap suggested by the Colorado Office of Consumer
Counsel.
"We're pleased with the decision, due to the
decision on cost recovery of $27.9 million," Bill
Levis, Colorado's Consumer Counsel, told me. "We
don't necessarily agree with the rationale.
"Whenever you're talking new technology, some
mistakes are made," Levis added, "but they can be
beneficial in the long run."
Levis meant that future grid modernization projects
likely will adopt a more inclusive approach for
stakeholders and regulators upfront, to avoid
outcomes such as SmartGridCity (SGC).
A few quotes from the CPUC's written decision will
spell out what, in my view, should have been
stipulated before a dime was spent.
"Public Service (aka Xcel) apparently experienced
difficulties with the planning and budgeting of the
project, and the costs associated with the project
quickly escalated from March 2008 to the filing of
the application in this docket," the CPUC wrote.
"However, standing alone, that does not mean
necessarily that the company acted imprudently. That
said, we are concerned whether SGC is today slated
to achieve enough of its potential to justify its
higher-than-anticipated costs ... We are also
concerned with the relative lack of details
regarding the planned use of the project going
forward.
"In short, we want to see the company articulate and
defend a strategic plan for the use of SGC
investment. We want to see a credible promise of
consumer and utility benefits sufficient to justify
the cost overruns. We want to know more about the
ability of customers to make practical use of SGC on
their side of the meter through in-home devices and
we want to know more about the interconnect ability
of SGC with those customer devices.
"We find that the record evidence about future use
of SGC is sparse. The most tangible portion of that
information addresses the pricing pilot and the
planned report to the commission on the value
propositions. This approximates the modified scope
of the project when it was considered in March 2009.
At that time the capital cost of the project was
$27.9 million and we therefore deem that level of
investment to be prudent at this time.
"In sum, this commission believes that the company
needs to 'reboot' the SGC project and restore some
of the promise that this concept originally held. If
the company demonstrates in a future application
that the SGC project has a coherent and valuable
future, we may allow the company to recover the
balance of the investment disallowed at this time."
That last statement is footnoted thus: "Such future
application should at a minimum summarize how
advisory groups are being engaged, identify smart
grid investments and how such investments (or the
knowledge gained) will benefit customers and grid
operations."
One point that should not escape us: if Xcel comes
through on these stipulations, it will in fact
recover all of that $44.5 million. That still falls
short of requiring balance between shareholder and
ratepayer risk.
Phil Carson is editor of Intelligent Utility
Daily

Copyright © 1996-2010 by
CyberTech,
Inc.
All rights reserved.
To subscribe or visit go to:
http://www.energycentral.com
To subscribe or visit go to:
http://www.energybiz.com