NRC wants more information about concrete condition at
Seabrook Station
Mar 31 - McClatchy-Tribune Regional News - Jim Haddadin
Foster's Daily Democrat, Dover, N.H.
Federal inspectors have confirmed a concrete condition found
in an underground tunnel at Seabrook Station poses no immediate
safety threat, but the Nuclear Regulatory Commission is calling
for more information about how the issue will be managed in the
future.
The plant operator has applied to have its operating license
extended from 2030 to 2050, but the application has been delayed
while the NRC reviews the concrete condition.
Tests showed groundwater has deteriorated some of the
concrete in the underground tunnel by more than 20 percent. The
discovery of prompted the NRC to delay a safety report connected
with the plant's request for a 20-year license extension.
NextEra representatives have said the issue has been dealt
with, the area in question is now dry and the structural
integrity of the concrete continues to meet standards.
The NRC this week issued the findings of the latest
inspection at Seabrook Station, which focused on NextEra's
analysis of the concrete issue.
Six inspectors visited the power plant during two separate
trips in September and November 2011 to evaluate the concrete
issue. An inspector also visited the Illinois laboratory where
NextEra's concrete testing is conducted to verify its procedures
are sound.
In a letter dated Monday, March 26, the director of NRC's
reactor safety division wrote the concrete condition poses no
immediate safety threat, but he instructed NextEra to be
prepared to discuss plans for future management at an April 23
meeting with the NRC.
"The inspectors concluded that these structures can currently
perform their safety related functions despite the observed
degradation due to (the condition)," Miller wrote. "However the
NRC still has concerns associated with long term operability,
therefore additional information is needed."
The NRC has requested more information about the effects
groundwater leakage might have on other parts of the tunnel,
such as the steel rebar that reinforces the concrete, as well
how fast ASR progresses and how aspects of the concrete will be
affected by the condition.
NextEra was also notified of two low-level violations, which
must be addressed in a pending action plan.
The NRC is requesting the corrective plan includes
information about the overall progression of the concrete issue,
its effects and its causes, as well as a list of actions to
correct or mitigate the issue and a timeline for key actions.
The degradation was caused by an alkali-silica chemical
reaction in concrete. Such a reaction occurs over time when
concrete is in contact with water. The alkaline cement paste and
reactive, non-crystalline silica found in some common coarse
aggregates can form a gel in the presence of water. The gel
expands and causes tiny cracks in the concrete, changing its
physical properties.
NRC representatives believe the decay is the first confirmed
instance of such deterioration in a safety-related concrete
structure at a nuclear plant in the United States.
Asked to comment on the inspection report, NextEra
spokesperson Al Griffith responded via email this week that the
operators are pleased the NRC has made clear there are no
immediate safety concerns at Seabrook Station. The plant has a
comprehensive strategy in place to effectively manage ASR,
Griffith wrote, which includes augmented monitoring, improved
analysis techniques and efforts aimed at mitigation.
"We share with the NRC the desire to complete ASR analysis
and testing so that we fully understand any potential long-term
impact ASR may have on our safety-related systems and
structures," he wrote.
One of the two low-level violations noted during the recent
inspections resulted from failure to fully evaluate the
potential "structural and seismic impacts" of the concrete
degradation, according to the inspection report. The second
minor violation stemmed from failure to re-evaluate a
"use-as-is" determination for certain safety-related structures
impacted by the concrete condition before implementing a design
change.
Sheehan said in addition to the two issues that were noted in
the inspection report, the NRC has previously documented three
other minor violations between May and August 2011. NextEra will
need to address all inspection findings in its corrective plan.
Asked if the company has met its obligations to the NRC to
assemble a long-term plan, Sheehan said the commission is "not
fully satisfied with the responses we've received back."
"We still need more information on their analysis on why the
buildings would be able, in the long term, to perform their
safety functions, and what kind of comprehensive plan the
company is developing to address that," he said.
The company was also scheduled to present an engineering
evaluation by the end of March.