Will Low Natural Gas Prices Eliminate the Nuclear Option in the US?
Posted on October 02, 2013
Posted By:
Robert Graber,
Thomas Retson
Topic:
Fossil & Biomass
A probabilistic comparison of the investment risks of nuclear
power and natural gas-based electricity generating plants has been
carried out using a total-lifecycle power plant model. Although the
cost of the gas plant (with carbon tax) is found to be slightly
cheaper, that choice of fuel carries a far greater cost uncertainty,
suggesting a greater long-term investment risk than nuclear power.
The results are shown in Figure 1 and 2, below. Figure 1 shows that the expected levelized generating cost of nuclear power over its 60-year lifetime to be about $87/MWh (all figures are in 2012 dollars). There is a 5% probability that the actual realized generating cost will exceed $99/MWh and a 5% probability that the realized generating costs will be below about $77/MWh. Stated equivalently, there is a 90% probability that the realized generating cost will be between $77/MWh and $99/MWh - a range of $22/MWh.
Figure 2, is the same comparison for a high efficiency natural gas plant using a combined cycle technology (and including a carbon tax). Because a second natural gas unit was assumed to be constructed after 30 years, this, introduces the prospect of the second plant having a higher capital cost than the first unit. This was accounted for by assuming that that the capital cost of a natural gas plant grows by 2% per year (in real dollars).
In the case of natural gas the expected value of generation is
about $84/MWh, lower than for the nuclear plant. However, the range
of uncertainty is higher for the natural gas plant. In this case the
90% probability range is over $38/ MWh, or nearly twice the range of
the nuclear plant. This is the result of the volatility of natural
gas over a long time frame and implies a greater investment risk if
a natural gas plant is chosen over a nuclear plant (as will be
discussed below).
Table 2, below illustrates typical results obtained using only the static (non-simulated) LCOE.2 There are two columns for natural gas, showing the costs both with and without environmental compliance costs - in this case a $25/ton CO2 carbon tax beginning in 2020. This chart clearly shows the tradeoff between capital costs and variable costs (fuel and environmental compliance) between nuclear and natural gas plants. But more important, it illustrates the risks of relying on static LCOE results. The contrast between the risk-adjusted results in Figures 1 through 3 and the point values of results in Table 2 is stark. It is particularly dangerous when making generating technology decisions owing to their dependence on a commodity with a market-derived price over a very long time. This is particularly true for natural gas exposed to not only supply and demand; but also the potential for climate change initiatives directed at carbon-emitting fuels.
The price of natural gas delivered to US electric utilities in
2012 was approximately $4.35/mmbtu. However, this price is
unsustainable as it is below the average cost of producing shale gas
- currently the major source of new drilling in the US-estimated at
between $5-8/mmbtu4. While the prospects that shale gas will extend
the supply of natural gas are positive, like any commodity the
cheapest and most easily mined supply will be produced first.
Further, LNG facilities in the US, once constructed to import LNG,
are being converted into export facilities as natural gas prices
measured in US dollars are as high as $16.50/mmbtu in Japan and
$9.00/mmbtu in the UK5
The coefficient of variability measures the amount of risk
(standard deviation) that an investor has to
It may be argued that decommissioning also represents a higher
risk for investors in the case of nuclear power. However, this is
already accounted for in Figures 1 and 3, and moreover, investors
have possibly up to 80 years before the decommissioning decision
must be made-resulting in an annuity that is easily managed. These
results are being validated in real life. In March, 2012 the US
Nuclear Regulatory Commission awarded combined construction and
operating licenses (COL) to two privately-owned nuclear plants in
the Southeast US: the Vogtle 3 & 4 units owned by Southern Company
and the Summer 2 & 3 units owned by South Carolina Electric and Gas.
(First nuclear concrete has recently been poured for Summer 2 and
Vogtle 3.) Both utilities obtained regulatory approval from their
respective state regulatory bodies, largely on the basis of fuel
diversity. It was precisely a reluctance to develop additional gas
resources on the very basis that it left both companies vulnerable
to increased fuel and regulatory compliance costs that was
instrumental in choosing nuclear-in spite of considerable opposition
from parties opposed to nuclear power. While coal would have been an
option, both utilities already have substantial coal capacity and
there is warranted anticipation that coal will be increasingly
targeted by the US Environmental Protection Agency for stringent
emissions controls, including, potentially, controls on CO2
emissions. A third utility-Florida Power and Light-is likely to also
be granted a COL for the construction of Turkey Point 5 & 6, and FPL
has made exactly the same fuel diversity case to the Florida Public
Service Commission. All of these regulatory agencies feel strongly
enough that nuclear power is essential that they granted the
utilities the ability to place their construction costs in the rate
base for recovery prior to actual plant operation-a first for U.S.
electric utilities.
Appendix B EPMM Simulation Model Key Assumptions
Figure B-2 shows the simulation model data used for the natural gas plants (Figure 2).
Finally Figure B-3 provides financial data used in both the nuclear and natural gas comparisons.
1 Levelized costs are useful as comparisons of costs between
generating technologies. They can be thought of as the equivalent
annual cost incurred over the life of the generating technology
having the same present value as actual costs which differ from year
to year.
Authored By:
Mr. Graber's is an energy economist with EnergyPath
Corporation - an energy and risk assessment consultancy
based in Wilmington, NC. He is the developer of
EnergyPath's proprietary EPMM software for performing
economic and risk evaluations of energy systems. Mr.
Graber spent over 20 years with GE's Power Systems
business in San Jose, California as the Company's Chief
Economist. Mr. Graber came to GE from Chase Manhattan
Bank in New York,
Authored By:
Mr Retson is president of EnergyPath Corporation. As
cofounder of EnergyPath in 2002, Tom guided the
formation and growth of this unique energy market
consulting firm which is broadly renowned for core
competencies within the global power and energy
industries. A 23 year career with GE Nuclear Energy
provided the foundation for Mr. Retson's move to
EnergyPath. Tom completed multiyear engineering
assignments before assuming progressively more
responsible US, European and
Copyright © 1996-2013 by CyberTech, Inc. All rights reserved. To subscribe or visit go to: http://www.energycentral.com To subscribe or visit go to: http://www.energybiz.com http://www.energycentral.com/generationstorage/fossilandbiomass/articles/2738 |