US Supreme Court won't hear challenge to grid cost-allocation ruling
Washington (Platts)--24Feb2014/211 pm EST/1911 GMT
In a decision that could help boost renewable energy projects, the US
Supreme Court on Monday refused to hear a challenge to a Federal Energy
Regulatory Commission decision that allowed an independent system
operator to spread among its members the cost of building long-line
electric transmission projects.
The high court's decision leaves in place a lower court's ruling that
held the commission properly considered and approved a tariff scheme
devised by Midcontinent Independent System Operator.
The 7th US Circuit Court of Appeals in June upheld FERC's reading of the
basic premise of broad cost allocation in the tariff that also lies at
the heart of FERC's Order 1000, a landmark rulemaking that addresses
cost allocation and regional planning for electric transmission
facilities.
Rejecting core objections raised by parties in Michigan and Illinois,
the circuit court judges maintained that the reasoning behind the
so-called "multi-value projects" tariff approved by FERC for use by MISO
was sound and that the tariff scheme figures to provide the entire
market region with benefits that are at least commensurate with costs.
Proposed in 2010, the MVP tariff "is mainly intended to finance the
construction of transmission lines for electricity generated by remote
wind farms" mostly in the Great Plains, the lower court said. MISO had
estimated that the cost of the lines will be more than offset by the
lower cost of electricity produced by the wind farms.
Under the approved tariff, the cost of the MVPs would be "allocated
among utilities drawing power from MISO's grid in proportion to each
utility's share of the region's total wholesale consumption of
electricity," thus placing most of the costs on urban centers where
demand for power is greatest, the appellate court said.
A group of petitioners led by the Illinois Commerce Commission had
argued that the criteria for determining which projects are eligible to
be treated as MVPs were not narrowly and properly defined.
As is customary when the high court denies cert, it gave no reason for
the decision.
--Chris Newkumet,
chris.newkumet@platts.com
--Edited by Jeff Barber,
jeff.barber@platts.com
© 2014 Platts, The McGraw-Hill Companies Inc. All rights reserved.
To subscribe or visit go to:
http://www.platts.com
http://www.platts.com/latest-news/electric-power/washington/us-supreme-court-wont-hear-challenge-to-grid-21258926
|