
The U.S. Nuclear Regulatory Commission (NRC) will
increase its oversight of the 670-MW
Pilgrim nuclear power plant in Massachusetts.
The enforcement action will move the plant into the
repetitive degraded cornerstone column, or Column 4, of the
NRC’s Action Matrix. The plant transitioned into the
degraded cornerstone column, or Column 3, in late 2013 as a
result of unplanned shutdowns and unplanned shutdowns with
complications the same year. NRC found in December 2014 that
plant owner and operator Entergy (NYSE:
ETR) did not adequately evaluate the causes of the
shutdowns and that some corrective actions had not been
completed or were closed out prematurely.
The latest finding was found during a special inspection at
the plant following an
unplanned shutdown in January 2015 caused by a winter
storm that left distribution lines inoperable. One of the
complications involved the failure of one of four safety
relief valves to open as part of the cool-down process. The
plant was already in Column 3 at the time of the shutdown.
Inspectors found that Entergy could have prevented the
failure if it addressed a previous relief valve issue from a
February 2013 storm that also shut down the plant.
The NRC will also determine the need for additional
regulatory action and examine the extent of equipment, human
performance and procedure quality issues that contributed to
or complicated the unplanned shutdowns. All of the safety
relief valves were replaced with ones of a different design
during a spring refueling maintenance outage. Entergy said
during a regulatory conference that two of the valves were
fully operational and the other two would have worked at
high-pressure levels.
NRC characterized the finding as a low-to-moderate safety
significance based, in part, on the determination that the
historical degradation of the valves indicated there was an
increased likelihood that the valves would not function when
needed.
Subscribe to
Nuclear Power International magazine.